BE projects run in phases, so plan backwards
Universities that award a BE degree, such as VTU, Anna University and Mumbai University, usually split the major project across the last two semesters. VTU's 2018 scheme, for instance, has a separate Project Work Phase 1 course in the 7th semester. Phase one is about the problem, the survey and the design. The real build happens in the next semester.
That split catches a lot of teams out. If your phase one presentation promises a feature, the panel will ask for it at the final review. Promise what four people can build in about four months, and keep the stretch goals in a separate "future scope" slide.
A simple plan that works for most BE teams
- Weeks 1-3: shortlist three topics, read a few papers or existing apps for each, and pick the one where you can say clearly what you will do better.
- Weeks 4-8: write the synopsis, draw the architecture and data flow, fix the dataset or hardware, and divide modules between members.
- Phase one review: problem statement, literature survey, objectives, architecture and a small working prototype if you can manage it. A prototype makes the panel far more relaxed.
- Final semester: build module by module, integrate early, test with real data, then write the report while the demo is being polished.
Topics that suit a four-member BE team
Pick something with natural parts. A computer vision attendance system, for example, has a camera pipeline, a model, a backend and a dashboard, so four people each own something real. A pure CRUD website rarely gives four people enough to explain in a viva. Browse the AI/ML, IoT and cybersecurity ideas on this page with that test in mind.